Galway Bay fm newsroom - Ireland has paid a 5 million euro fine to the European Commission in connection with the construction of Derrybrien Windfarm in South Galway

Advertisement

The State was found to be in breach of environmental safeguards, and additional daily fines of €15,000 are being imposed until the situation is rectified.

In November, the European Court of Justice ruled that Ireland must comply with a 2008 instruction to properly examine the consequences of the development at Derrybrien.

Advertisement

The case centred on long standing concerns about the impact of the 70 turbine development on the Slieve Aughty mountains.

The wind farm is operated by a subsidiary company owned by the ESB, which also built it

During the construction phase in 2003, a massive landslide occurred

The Department of Housing, Planning and Local Government is awaiting an update on what the ESB intends to do to comply with the European Court of Justice ruling.

No work has been carried out on the Derrybrien site to date and it's understood the ESB is finalising a programme of action that would regularise the development.

95.8 MHz Galway City
95.8 MHz Clifden & West Connemara
97.4 MHz South Connemara & Aran Islands
96.8 MHz County Galway
97.4 MHz East Galway
97.2 MHz Gort Area

Copyright © 2024. Developed by Square1 and powered by PublisherPlus.com

Download the GBFM App
Advertisement