Galway Bay fm newsroom - The early stage of vital flood relief works planned for South Galway have suffered another major delay.

Advertisement

That's according to the South Galway Flood Relief Committee, who say the project feasibility phase is already a year behind schedule and will now be delayed a further 6 months.

The original delay was due the gathering of data for the generation of computer models of the region's topography, and additional work in the public consultation process.

Advertisement

However, the committee say they have not been informed of the reason for the new delay in the process.

Spokesman for the South Galway Flood Relief Committee, David Murray, says hopes for works to begin in 2020 have been dashed.

For more, tune into Galway Bay fm news at...

95.8 MHz Galway City
95.8 MHz Clifden & West Connemara
97.4 MHz South Connemara & Aran Islands
96.8 MHz County Galway
97.4 MHz East Galway
97.2 MHz Gort Area

Copyright © 2024. Developed by Square1 and powered by PublisherPlus.com

Download the GBFM App
Advertisement